PRODUCT OWNER
Eau de Paris
CONSTRUCTOR
Eau de Paris
COMPANY(IES)
Bonna TP / Atlantique TP
CONSTRUCTION DATE
2019
LOCATION
Boulevard Gouvion-Saint-Cyr Paris 17ème (75)
As part of the construction project to build the T3 tram line in western Paris, EdP rerouted a domestic water main away from the tram line. This work was carried out in the 17th district of Paris, under boulevard Pershing and boulevard Gouvion Saint Cyr.
BONNA TP supplied 575 metres of DN1200 RCCPs (Reinforced Concrete Cylinder Pipes) with SL welded joints, 330 metres of which were laid by our construction teams, as well as a prefabricated chamber for a flow meter.
The pipes were laid in trenches in a highly built-up area near Porte Maillot in Paris.